Gretna Buc-ee's Plans Start With the Highway 6/31 Interchange

November 5, 2026

If you leave I-80 at the Highway 6/31 exit, Nebraska Crossing is on one side and Flying J Plaza is on the other. Across from Flying J, on about 43 acres southeast of I-80 and Highway 31, Buc-ee's plans to build its first Nebraska travel center. Most of the talk is about the store. The first change Gretna drivers will actually see is at the exit itself.

Buc-ee's has said the road work comes first. Its real estate director, Stan Beard, told KETV in July that "the construction on the intersection will come first, and then they will break ground on the store." So the next stretch of this project depends on interchange plans, NDOT coordination and bridge work more than on brisket and beaver plush.

The order of work, as officials have described it

Since January, the project has moved in steady steps through Gretna City Hall. Here is the sequence so far, and what officials expect next:

  1. Annexation. On Tuesday night, January 20, 2026, the Gretna City Council gave initial approval to annex the roughly 43-acre tract. The Nebraska Examiner reported that the land had to be inside city limits to qualify for Good Life District incentives.
  2. Use permit and preliminary plat. On May 19, the council approved Buc-ee's request to run a travel center near Highway 31 and Platteview Road, along with the preliminary plat.
  3. Final plat. By late July, the council had approved the final plat for the development, which carries the name Platte River Beaver Habitat.
  4. Incentives. At its Wednesday meeting at the end of July, the council approved the Good Life District incentives. KETV reported that this gave Buc-ee's what it needed to start the build.
  5. Land closing. The city's Fall 2026 mayor's newsletter says Buc-ee's has closed on its property and that building and engineering plans are still moving forward.
  6. Interchange plans and groundbreaking. The same newsletter expects interchange plans to be finished this winter, with construction and a groundbreaking that could begin in early spring.

As of this week, the project sits between steps five and six. The land deal is done, and the road design is still being finished.

What a diverging diamond changes at the exit

The rebuilt interchange will be a diverging diamond, Gretna city engineer Greg Perry told the Douglas County Post-Gazette. Between the ramps, traffic briefly crosses to the left side of the road. That lets drivers turn left onto I-80 without crossing oncoming traffic, and it cuts down on crash points and signal phases.

Perry said the plan has three lanes each way, northbound and southbound, with a trail down the middle that eventually moves to the east side as it reaches the Buc-ee's property. A pedestrian bridge will cross the highway so people can walk between Flying J Plaza and Buc-ee's. Councilmember Kara Alexander described the first few drives through one in the same Post-Gazette report:

"If you're not used to it, it's a little nerve-racking when it crisscrosses and crosses back. But it has a lot less points, so it's significantly safer."

The redesign was already in the works before Buc-ee's arrived. Perry said NDOT had been planning it for a few years and that the Buc-ee's project sped it up. City Administrator Paula Dennison put the interchange work at about a year. She said it can run at the same time as construction of the store.

For anyone who uses this exit every day, Perry's comments on disruption matter most. He said most of the work won't seriously affect traffic. The bridges on both sides need to be widened by about 2.5 to 3 feet for the new lanes and trail, and that work can be done overnight.

The store is expected to pay for the interchange

The newsletter puts the interchange at $23 million and calls it a state improvement. The city expects the whole cost to be covered by state sales tax collected at Buc-ee's. That money comes from Nebraska's Good Life District law, first passed in 2023. The Nebraska Examiner explains that the law cuts the state sales tax inside a designated district in half, from 5.5% to 2.75%, and uses the difference to help pay for district development. Gretna's district covers about 2,000 acres around Nebraska Crossing and is one of five in the state.

In January 2025, Gretna voters approved a city program that set up a replacement sales tax in the district, WOWT reported. It passed with 50.4% of the vote and gives the city broad control over how that money is spent inside the district.

KMTV reported that the incentive package gives Buc-ee's about $30 million in tax reimbursements. Part of that money goes toward redoing the Highway 6/31 and I-80 interchange in partnership with NDOT. Mayor Mike Evans told KETV, "two-thirds of this money is going to public infrastructure, and it's all being paid from the sales tax from Buc-ee's." He made a similar point in the Post-Gazette, saying the interchange "needed to probably be done, anyway."

This explains why the road comes first. The interchange is what the incentive deal pays for, and the store's future sales are the money that pays for it.

The exit is one of several Gretna roads changing in 2027

The interchange isn't the only road project on Gretna's calendar. In the same Fall 2026 newsletter, the city calls the coming work some of the most significant road improvements in its history, with most of it south of Highway 370. Three projects are expected in 2027:

  • 192nd Street, Segment 2: Highway 370 to Schram Road, widened to five lanes with a center turn lane or median.
  • 192nd Street, Segment 1: south of Schram Road, paved to five lanes with a center turn lane or median.
  • Capehart Road: west of 192nd Street, paved to three lanes.

The newsletter also lists NDOT's I-80 Sarpy County interchange for 2028. Its detour map routes traffic along Highway 370, Highway 50, Capehart Road, 180th Street, Fairview Road, 204th Street and Highway 6. The city notes that schedules can change and says it will post updates, affected areas and alternate routes at gretnane.org as each phase gets closer. If spring brings work at Highway 6/31, it will be one of several projects underway around town.

What arrives at the end of the line

The store is on a longer timeline. Dennison told the Post-Gazette in July that developers planned to start construction in late 2026 or early 2027, with about 18 months of work after that. Buc-ee's told KETV the same month that it hoped to hold the groundbreaking ceremony early next year. In May, city officials told WOWT they expected construction to wrap up in late 2028.

The finished store is planned at 74,000 square feet with 100 gas pumps. The Post-Gazette notes that this makes it one of the company's larger locations. KMTV reported that council documents project more than $35 million a year for Gretna and about 175 jobs, with starting pay projected at $19 to $22 an hour. Evans told KMTV he hoped permitting for the interchange would be finished by the end of the year.

The land has its own history. Joe Addleman told WOWT that the site was once his mother's family homestead and that the Gillespie family settled it in the late 1890s.

For now, the exit by Nebraska Crossing looks the way it has for years. The first visible sign of Buc-ee's will most likely be an NDOT crew working on the Highway 6/31 bridges overnight, sometime after the plans are finished this winter.

Big projects like this change how people get around Gretna, and they often come up when families weigh where to live in the area and how they'll get there each day. If you'd like to talk about how the interchange work and the 2027 road schedule affect a home you own or one you're considering near Highway 6/31 or 192nd Street, Staci Mueller Group is glad to help.